Harmony Construction Update – November 2017

Harmony Construction Update – November 2017

Harmony’s Sales and Information Centre is now open to the public and works are almost complete on Harmony Display World, set to launch on Saturday 18 November 2017.

The intersection of Claymore Road and Sippy Downs Drive is currently being upgraded to include a second northbound lane on Claymore Road. Construction is progressing well with the upgrade works expected to be completed later this month.

AVID Property Group would like to thank you for your patience and understanding during construction and apologise for any inconvenience caused.

If you have any questions, please contact the team at harmony@avidpropertygroup.com.au.

Harmony Construction Update – October 2017

Harmony Construction Update – October 2017

Harmony’s Sales and Information Centre is now open to the public and construction is going full steam ahead, with Harmony’s Display World set to open in mid to late November. The first residents at Harmony will be moving in to the community in the coming weeks.

The sewer rising main adjacent to the Albany Street and Bainbridge Circuit intersections was recently relocated by Unitywater allowing the Bainbridge Circuit and Claymore Road intersection to be completed.

The intersection of Claymore Road and Sippy Downs Drive are also being upgraded to include a second northbound lane on Claymore Road. Construction is progressing well with the upgrade works expected to be completed in November.

AVID Property Group would like to thank you for your patience and understanding during construction and apologise for any inconvenience caused.

If you have any questions, please contact the team at harmony@avidpropertygroup.com.au.

Harmony Construction Update – June 2017

Harmony Construction Update – June 2017

Construction is progressing well on Harmony Display World with slabs now laid and frames taking shape.

 

Builders will be getting on site this month to start construction on homes as part of the first land release as properties start settling from 19 June.

 

Asphalt, line marketing and landscaping is now complete along Claymore Road. A sewer rising main adjacent to Albany Street will be relocated in July. This will allow the final street lights and guard rail to be installed along the eastern side of the Claymore Road at this location.

 

Peter Crosby Way, the gateway to Harmony, is officially opening on Monday 26 June 2017.

 

AVID Property Group would like to thank you for your patience and understanding during construction and apologise for any inconvenience caused. If you have any questions, please contact the team at harmony@avidpropertygroup.com.au.

 

Harmony Construction Update – May 2017

Harmony Construction Update – May 2017

Construction is going full steam ahead at Harmony, with the majority of works along Claymore Road and the Red Cedar Street/ University Way intersection scheduled for completion this month.

 

Harmony’s main entry road, Peter Crosby Way, is also on track to open in June. Construction is also progressing on Harmony Display World with builders busy constructing slabs for 43 display homes this month.

 

The following activities are planned for May along Claymore Road:

  • Kerb and median island construction
  • Installation of street light poles and traffic signals
  • Sealing and asphalting (Claymore Road widening and University Way)

 

Detours

There will be a stop/ go system in place where road widening works are occurring on Claymore Road at the intersections of Bainbridge Circuit, Albany Street, Fitzwilliam Drive, University Way and Red Cedar Street. This will occur intermittently to allow for the installation of street light poles and traffic signals.

 

Once the roads are sealed with asphalt, southbound traffic from Claymore Road will be diverted onto the newly constructed lanes of University Way to allow roadworks to be completed within the work zone of University Way.

 

Northbound traffic on University Way leading into Claymore Road will continue to use the left hand lanes.

 

The Red Cedar Street/ University Way intersection will continue to use the guided traffic diversions in place while median islands are being constructed.

 

 

Road closures

There may be a road closure along University Way intermittently throughout May during work hours only. This will not be a permanent road closure. Buses will be accepted and escorted through the closure.

 

 

AVID Property Group would like to thank you for your patience and understanding during this time and apologise for any inconvenience caused during construction. If you have any questions, please contact the team at harmony@avidpropertygroup.com.au.

 

Harmony Construction Update – April 2017

Harmony Construction Update – April 2017

Construction is progressing well at Harmony. Please see our April Construction Update below for details.

This month, our builder partners will visit their lots at Harmony Display World and soon commence construction of the display village.

Despite delays due to wet weather, the installation of sewer rising main across Claymore Road is now complete.

The following activities are planned this month for works along Claymore Road:

  • Kerb construction
  • Asphalt works at Bainbridge Circuit, Albany Street, Fitzwilliam Drive, Claymore Road, University Way and Red Cedar Street
  • Installation of traffic signals and electrical conduits
  • Installation of street lights
  • Line-marking

Detours:

There may be two detours used intermittently in April during work hours only along University Way. These will not be permanent detours. The detours will allow our contractors to facilitate kerb works along University Way.

Potential road closures:

AVID advises of a potential road closure to occur intermittently throughout April during work hours only along University Way. This will not be a permanent road closure. Buses will be accepted and escorted through the closure. This will allow our contractors to complete construction of concrete median islands and kerb works along University Way.

There will also be lane closures and shoulder closures from time to time at each intersection along Claymore Road during April. This will facilitate the completion of asphalt works at each intersection, and the installation of traffic signal and electrical conduits.

Weather permitting, it is expected that most intersection upgrades will be nearing completion by the end of April, with testing and commissioning of traffic signals, and electrical works to follow.

AVID Property Group would like to thank you for your patience and understanding during this time and apologise for any inconvenience caused during construction. If you have any questions, please contact the team at harmony@avidpropertygroup.com.au.