Good afternoon everyone,

I’d like to update on you the work that has been completed over the past 8 weeks on Bundilla Blvd at Mountain Creek.

Works to date have included:

– Road widening for cycle lanes on either side.

– New bitumen seal from Karawatha Drive to Manatunga Parade which is much smoother, safer and less noisy for residents living near the road.

– 200 new trees to replace those lost for the upgrade.

– New footpaths.

– New bus shelter.

– Improved drainage.

– Current bridge railings being taken away and repainted/coated.

You will also note that there are pedestrian refuge points for people to cross the road safely only having to cross one lane at a time.

Please see the attached photos as an update.

Kind regards,

Christian